Two-storey house clad in vertical cedar and blackened steel, set behind a low board-formed concrete garden wall
Plate 01 — Croisan Creek Residence, South Salem
01 New custom home

Croisan Creek Residence

A house that had to sit quietly on a loud lot.

Location
South Salem
Scope
3,240 sf · 4 bed · Design-build
Duration
11 months
Completed
2025

Project note

The site drops eleven feet from the street to the creek easement, which ruled out a standard stem-wall foundation and most of the buildable footprint. We stepped the house across three slabs instead, so the garage sits at street grade and the living floor lands eight feet lower, level with the tree canopy. Exterior is rough-sawn western red cedar on a rainscreen with blackened steel at the entry; the garden wall is board-formed concrete poured on site with the client's own Douglas fir forms. Because the creek buffer required a stormwater plan before we could break ground, we ran permitting and structural engineering in parallel with design and still opened the ground in April.

Foundation
Three-level stepped slab
Cladding
Rough-sawn WRC rainscreen
Notable
Board-formed concrete garden wall
Open-plan living and kitchen with a white oak feature wall, pale concrete floor and a wall of glass to the garden
Plate 02 — Fairmount Hill Whole-Home Remodel, Fairmount Hill, Salem
02 Whole-home remodel

Fairmount Hill Whole-Home Remodel

Ninety-nine years of additions, taken back to one idea.

Location
Fairmount Hill, Salem
Scope
1926 Tudor · 2,780 sf · Full gut
Duration
7 months
Completed
2025

Project note

Four owners had each bolted something onto the back of this Tudor, and the result was six small rooms with no natural light and a kitchen you entered sideways. We removed the two rearmost additions entirely, exposed the original 2x8 rafters, and replaced a bearing wall with a flush-framed steel beam so the kitchen, dining and living could share one 34-foot run. Everything structural got brought current — new shear panels, a seismic retrofit at the cripple wall, and a full rewire off a 200-amp service. The white oak wall is quartersawn and site-finished; the floor is a polished topping slab over the original crawlspace fill.

Structure
Flush steel beam, seismic retrofit
Systems
Full rewire, 200-amp service
Notable
34 ft clear span, no dropped header
Interior of an A-frame cabin with exposed Douglas fir rafters, a loft, and a compact kitchen under the slope
Plate 03 — Rickreall Ridge A-Frame, Polk County
03 Restoration & rebuild

Rickreall Ridge A-Frame

A 1971 A-frame with a good frame and nothing else.

Location
Polk County
Scope
1,150 sf · Structural rebuild
Duration
6 months
Completed
2024

Project note

The owners bought it for the rafters — clear Douglas fir, 4x10, on 4-foot centers — and almost everything else had to go. We jacked and re-shimmed the ridge where a 1990s skylight cut had let water into the beam pocket, sistered four rafters, and replaced the entire roof assembly with a vented over-framed system so the fir could stay exposed inside. The loft stair was rebuilt to code without widening the footprint by turning the run 90 degrees and borrowing eight inches from the kitchen. Rural site, no municipal water: we coordinated a new well, pressure tank and septic drainfield alongside the structural work.

Structure
Ridge jack, four sistered rafters
Envelope
Vented over-framed roof, R-49
Notable
Well, pump & septic coordinated on site
Office corridor lined with steel-framed glass partitions, polished concrete floor and pendant lighting
Plate 04 — Broadway Street Tenant Improvement, Downtown Salem
04 Light commercial

Broadway Street Tenant Improvement

Fourteen weeks, an occupied building, and a hard opening date.

Location
Downtown Salem
Scope
4,100 sf · Office & clinic fit-out
Duration
14 weeks
Completed
2025

Project note

A shell floor above two operating businesses, converted into offices and four exam rooms. The constraint was noise and access: no demolition before 9 am, no elevator use during lunch service downstairs, and a fire alarm that couldn't be taken offline for more than four hours at a stretch. We phased the work in three zones so inspections could run rolling rather than all at the end, and pre-assembled the steel-framed glass partitions off site to cut on-floor time roughly in half. Certificate of occupancy landed nine days ahead of the tenant's lease commencement.

Constraint
Occupied building, restricted hours
Method
Three-zone phasing, rolling inspections
Notable
C of O nine days early
Charcoal-tiled bathroom with a freestanding tub below a long clerestory window and a floating vanity
Plate 05 — Candalaria Primary Suite Addition, Candalaria, Salem
05 Addition

Candalaria Primary Suite Addition

A 520-square-foot addition that reads as original.

Location
Candalaria, Salem
Scope
520 sf addition · Suite & bath
Duration
4 months
Completed
2024

Project note

The existing 1958 ranch had a good roofline and a bad primary bedroom. Rather than push a box off the back, we extended the existing hip at the same 4:12 pitch and matched the roof plane exactly, which meant re-framing eleven feet of the original ridge. The new bath sits under a 9-foot clerestory that pulls south light across the ceiling without giving the neighbours a view in. Radiant floor on its own zone, a linear drain set flush to the tile, and a whole-house fan added while the ceiling was open. From the street you cannot tell where the house stops and the addition starts, which was the whole point.

Roof
Existing hip extended, 4:12 matched
Comfort
Radiant floor, dedicated zone
Notable
Clerestory daylight, no sightlines
Wide open living room with a full wall of sliding glass opening onto a covered terrace
Plate 06 — Keizer Rapids Great Room, Keizer
06 Structural remodel

Keizer Rapids Great Room

Take out the wall. Keep the house standing.

Location
Keizer
Scope
Wall removal & envelope · 1,400 sf
Duration
5 months
Completed
2023

Project note

The client wanted the entire south wall of the house to be glass. That wall was carrying the second floor. We designed a moment frame with the structural engineer, cut in a 28-foot glulam on steel columns hidden inside the remaining piers, and temporarily shored the second storey on adjustable posts for eleven days while the frame went in. The sliding units are 10-foot panels on a flush track set into the slab, so the terrace reads as the same floor. Envelope was upgraded at the same time — new sheathing, taped WRB and continuous exterior insulation on all four elevations.

Structure
28 ft glulam on hidden steel columns
Method
Second storey shored for 11 days
Notable
Flush slab track, indoor/outdoor floor

Also on the books

Two hundred and fourteen projects since 2006 — and nine in the ground right now.

If you'd like to walk an active site, we can usually arrange it with a week's notice. Seeing how a job is run mid-build tells you more than any finished photograph.

Ask about a site walk